The Story Behind The Project
Project Overview
ElectraNet’s hill to hill transmission line project involved building a large transmission line from Port Augusta to Roxby Downs in South Australia providing Prominent Hill mine with direct access to the main electricity grid. The project involved 1128 structures spanning over 270kms.
- Provide all identification and safety signage
- Total of 1128 different structures
- It had a high volume of variable data
- Provided over 5,000 signs for this project
- Tax Minimisation Strategies
What Needed To Be Solved
Challenge
Having signs that would withstand the harsh Australian UV and weather conditions was crucial for this project. As the project spanned over 270km the cost of sign replacement is high due to the remote location and expansive area the transmission line covers.
The next challenge was ensuring a smooth installation process for the installation teams. As the project spanned across such a large area, the accuracy of variable data and the order it was packed in was a high priority.
To ensure the project was completed on time the signs for all 1128 structures had to be installed.
Identimark produced and delivered all items to the site for installation on time to avoid commissioning delays which would incur penalties for the contractor.
The Solution We Provided
How We Helped
Using U3 signs on this project were specified which meant that all signage would last and withstand the harsh conditions without fading or breaking, for life.
With a high volume of variable data Identimark labelled and packed each sign set so all items were in the correct order and that all cartons were numbered so the installation team could easily find the items required.
To ensure the project was completed on time the signs for all 1128 structures had to be installed.
Identimark produced and delivered all items to the site for installation on time to avoid commissioning delays which would incur penalties for the contractor.
Products
Used In This Project
U3 SIGNS - THE LONGEST LASTING SIGN